Providing supervision services for the implementation of 6 (six) yellow fidic type works contracts for the proper management of works contracts and the successful completion of the project as follows:

>> Cl1: expansion of the treatment plant and construction of the sludge incinerator;

>> Cl2: construction of the drainage system on the right side of the box and other works on the drainage system from the Titan, Tienretului and Carol lakes;

>> Cl3: rehabilitation of the main sewer collectors (a0 and b0)

>> Cl4: rehabilitation of the box and its main drainage system on the left side of the box (in the Ciurel-Unirii-Vitan sectors)

>> Cl5: rehabilitation of the box (in the Vitan-Glina sector)

>> Cl6: rehabilitation/replacement of the sewer network (in the Cotroceni, Regina Maria and Tienretului areas)